Posted in | News

Granite ConstructionTemporarily Cease Work on $130 Million Highway Realignment

Granite Construction Incorporated today announced that Granite Construction Company, a wholly owned subsidiary, and the Oregon Department of Transportation ("ODOT") have reached an agreement in principal on a negotiated temporary suspension of the US 20 Pioneer Mountain to Eddyville Design-Build project.

ODOT awarded the $130 million highway realignment contract to Yaquina River Constructors ("YRC"), a joint venture team comprised of Granite Construction Company and Wilder Construction Company (a majority-owned subsidiary of Granite Construction Company) in July 2005. The design for the new seven-mile roadway included eight bridges to be constructed over creeks, rivers, and a railroad. During the course of construction, numerous and massive landslides at critical sections of the project were discovered. As a result of additional anticipated costs and time related to these landslides, in March 2007, Granite requested that ODOT either terminate or suspend its contract.

After several months of negotiations, Granite and ODOT have agreed that in lieu of terminating the contract, it is in the best interest of the parties to temporarily suspend work. This suspension will allow time for both parties to jointly complete additional geotechnical site investigations and explore alternative, less expensive landslide mitigation solutions. Under the terms of the agreement, construction work on the project will be suspended beginning on or about September 1, 2007 and will resume no earlier than June 1, 2008. During the suspension period, a small team of YRC management will remain on the project to ensure that all environmental protection measures are maintained. Costs associated with the temporary suspension will be shared between ODOT and Granite.

The negotiated temporary suspension agreement, however, does not stipulate responsibility for the landslide mitigation costs. Both parties have agreed to take the issue to the standing Dispute Review Board ("DRB") under the dispute resolution provisions of the contract. Upon resolution of this issue, and agreement on the final cost and schedule to complete the project, Granite will restart construction under a signed change order issued by ODOT with no associated unresolved revenue issues or disputes.

At March 31, 2007, the US 20 project was forecasted at a loss of approximately $20.0 million. Although Granite believes there is the potential for this amount to be reduced, there is remaining uncertainty surrounding the ultimate determination of responsibility for the landslide mitigation costs. As a result, we do not anticipate recording any adjustments to our project forecast during the quarter ended June 30, 2007.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.