Aug 27 2010
Larsen and Toubro Limited (L&T) has bagged two projects worth Rs 1195 crore from ONGC to set up Additional Processing Units at its Gas Processing complexes at Hazira and Uran.
The Additional Processing Units (APU) project at Uran complex shall enhance the Gas Processing capacity at the Uran complex by 5 MMSCMD. New facilities to be setup include a Gas Sweetening Unit (GSU), LPG Recovery Unit (LPG), Condensate Fractionation Unit (CFU), Condensate Handling Unit (CHU) and other Utilities.
The Additional Gas Processing Facilities (AGPF) project for Hazira complex is for augmenting the Gas Processing capacity in the Hazira complex by 5.6 MMSCMD . New facilities to be set up include a Gas Sweetening Unit (GSU), Gas Dehydration Unit (GDU), Dew Point Depression Unit(DPDU) and Offsite & Utilities.
The scope of the contract includes Project Management, Residual Basic Design, Planning & Monitoring, Residual Process Engineering, Detailed engineering, Procurement, Supply, Fabrication, Manufacturing, Inspection, Transportation, Storage, Construction, Installation, Testing, Mechanical Completion, Precommissioning, Commissioning, Performance Guarantee run test and handing over of New Process Units, Offsite and Utilities to the owner.
In the past, L&T has worked for establishing Onshore Gas Processing complexes for Reliance Industries Limited at Kakinada and Cairn Energy at Barmer. With significant growth potential in the Natural Gas market, these orders further reinforce the customers’ confidence in L&T’s capability to execute large orders in the Onshore Gas Processing area. The orders are also a testimony to L&T’s leadership position in the Engineering & Construction segment.